Lifecycle Stage
1. Discover2. Triage3. Design4. Approve5. Deliver6. Verify7. Embed, Scale or Close
Stage Gates
- Baseline ApprovalHead of Sustainability, SPG · 2025-01-15Baseline data verified against CEMS recordsApproved
- Business Case ApprovalCFO, SPG · 2025-02-10Approved within FY25 capital planApproved
- Technical ReviewChief Engineer, SPG · 2025-03-01Approved
- Funding ApprovalGroup Capital Committee · 2025-03-20Approved
- Evidence ReviewGroup ESG Lead ·Awaiting Q2 monitoring dataIn Review
- Claim ApprovalPending
Milestones
| Milestone | Owner | Due | Status |
|---|---|---|---|
| Complete combustion optimisation study | Plant Engineering Manager | 2025-06-30 | Complete |
| Install upgraded burners Unit 1 | Chief Engineer, SPG | 2026-03-31 | In Progress |
| Install upgraded burners Unit 2 | Chief Engineer, SPG | 2026-09-30 | Not Started |
| Verify emissions intensity reduction | Group ESG Lead | 2027-06-30 | Not Started |
Measurement (Metrics)
| Metric | Category | Unit |
|---|---|---|
| Scope 1 GHG Emissions Intensity | outcome | tCO2e/MWh |
| Plant Heat Rate | output | kJ/kWh |
Evidence
| Evidence | Type | Status |
|---|---|---|
| CEMS Q1 2025 Data Export | source-system extract | Approved |
| Combustion Optimisation Study Report | monitoring report | Approved |
Updates, Decisions & Comments
status
Combustion optimisation study complete; results confirm 4% heat rate improvement is achievable
Plant Engineering Manager · 2026-07-06 01:44:16
risk
Supply chain delay risk identified for burner components - alternative supplier being sourced
Plant Engineering Manager · 2026-07-06 01:44:16