Migrant Worker Recruitment Fee Remediation — Project Canvas

  Group ESG Lead
← Back to Project Workspace Edit Canvas

A. Project Context

Sponsor
Group Head of HR
Manager
HR Business Partner, SPG
Participating Organisations
Southern Power Generation Sdn Bhd, Ash Handling Co
Asset / Location
Selatan Coal Power Station
Reason for Action
Repay recruitment fees improperly charged to migrant contract workers to remediate an actual harm already identified

B. Baseline

Current Situation
Audit identified 42 contract workers charged recruitment fees averaging RM 3,200 per worker by labour agent
Baseline Date
2025-04-01
Baseline Metrics
Data Quality
Counterfactual

C. Objectives

Intended Change
Full repayment of identified fees plus process correction
Target
100% of affected workers repaid and contractor process corrected
Target Date
2025-09-30
Affected Stakeholders
Ash handling contract workforce
Expected Benefits
Direct remediation of harm, reduced forced labour risk, improved contractor compliance

D. Options

Alternatives Considered
Do-Nothing Case
Reason Selected

E. Cross-Pillar Effects Review Reviewed

Could solving this problem create a different environmental, social or governance problem?

Potential Trade-offs / Unintended Consequences

F. Safeguards

Rights & Stakeholder Impacts
Environmental Impacts
Community Impacts
Mitigation Measures
Grievance Requirements

G. Business Case

Capital Cost
RM 180,000
Operating Cost
Savings
Revenue
Avoided Cost
Funding Source
Risk Reduction
Strategic Value

H, I, J. Measurement, Evidence & Governance

See linked Metrics, Evidence, Stage Gates and Governance in the Project Workspace tab.